Tennis & Basketball Court Resurfacing

Over the course of July and August, SAMLARC will conduct repairs to various baketbal and tennis courts throughout the community. These projects maintain the aesthetic and structural integrity of the facilities, ensuring that Members and their guests can continue to enjoy playing sports together throughout the year. The project will be completed according to the following schedule (weather or materials delays excepting):

  • June 26 - July 12: Trabuco Mesa Park (1 basketball court, 2 tennis courts)
  • July 9-19: Monte Vista Park  (1 basketball court, 2 tennis courts)
  • July 22-23: Cielo Vista Park (2 tennis courts)
  • July 24-30: Mesa Linda Park (1 basketball court)
  • August 1-9: Solana Park (1 basketball court)

For questions regarding this project, contact Devin Swanson, Capital & Reserve Project Manager, at devin.swanson@fsresidential.com.