Community Concrete Repair Project

The concrete pathways throughout several SAMLARC parks will undergo repair throughout the months of September and October. The project is anticipated to conclude in mid-October, pending unanticipated weather delays. Sidewalk access may be limited in certain areas during each project phase. 

The project schedule is anticipated to be completed according to the following sequence:

  • Altisima Park: Tuesday, 9/3 – Wednesday, 9/4
  • Estrella Vista Park (includes 1 Concrete Replacement): Thursday, 9/5 – Friday, 9/6
  • Solana Vista Park: Monday, 9/9 – Tuesday, 9/10
  • Arroyo Vista Park: Wednesday, 9/11 – Thursday, 9/12
  • Canada Vista Park: Friday, 9/13 – Monday, 9/16
  • Mesa Linda Park: Tuesday, 9/17 – Wednesday, 9/18
  • Tijeras Creek Park: Thursday, 9/19 – Friday, 9/20
  • Trabuco Mesa Park: Monday, 9/23 – Tuesday, 9/24
  • Lakeshore: Wednesday, 9/25 – Thursday, 9/26
  • Monte Vista Park: Friday, 9/27 – Monday, 9/30
  • Cielo Vista Park: Tuesday, 10/1 – Wednesday, 10/2
  • Central Park (includes 1 Concrete Replacement): Thursday, 10/3 – Friday, 10/4
  • Vista Verde Park: Monday, 10/7 – Tuesday, 10/8

For questions regarding this project, please contact Devin Swanson, Project Coordinator, at devin.swanson@fsresidential.com.