Parks & Lake Concrete Project

SAMLARC's professional service providers will be repairing concrete panels throughout several SAMLARC parks and the Lakeshore over the next four weeks. Proactively addressing concrete conditions ensures that walking surfaces remain safe and last for many years to come. The parks and Lakeshore will remain open during the project and pedestrian impacts will be minimal. The project schedule is as follows (weather permitting):

  • Beach Club/Lakeshore – (4 days) – 4.10.23 - 4.13.23
  • Trabuco Mesa Park – (2 days) – 4.14.23 - 4.16.23
  • Tijeras Creek Park – (1 day) – 4.17.23
  • Arroyo Vista Park – (3 days) – 4.18.23 - 4.20.23
  • Mesa Linda Park – (0.5 day) – 4.21.23
  • Canada Vista Park - (2 days) – 4.21.23 - 4.24.23
  • Cielo Vista Park – (1 day) – 4.25.23
  • Vista Verde Park – (1 day) – 4.26.23
  • Monte Vista Park – (1 day) – 4.27.23
  • Central Park (1 day) – 4.28.23
  • Estrella Vista Park – (0.5 day) – 4.28.23
  • Solana Park – (1 day) – 4.28.23 - 5.1.23
  • Altisima Park – (2 days) – 5.2.23 - 5.3.23

For questions regarding this project, please contact Devin Swanson, Project Coordinator, at devin.swanson@fsresidential.com.